Task no. | Task | Start date | Completion date |
1 | Scaffold specification to be prepared, including a fan to catch loose stonework | 03/12/2014 | 10/12/2014 |
2 | Send specification to scaffold installer to obtain competitive prices | 10/12/2014 | 10/12/2014 |
3 | Receive prices from scaffold contractors | 17/12/2014 | 17/12/2014 |
Agree lease/licence structure with all parties | 20/12/2104 | 20/12/2014 | |
5 | Selected scaffold installer instructed to errect scaffold | 02/01/2015 | 02/01/2015 |
6 | Scaffold erected | 06/01/2015 | 10/01/2015 |
7 | Loose pieces removed from turrets and covering adjusted and enhanced to ensure loose pieces in the future are secured | 10/01/2015 | 15/01/2015 |
8 | Grant funding options considered; HLF application prepared; matched funders approached | 15/01/2015 | 01/06/2015 |
Heads of terms agreed | 01/02/2015 | 01/02/2015 | |
4 | Draft lease/licence documentation circulated for comments/agreement | 01/04/2015 | 01/04/2015 |
Lease/licence agreement signed | 01/05/2015 | 01/05/2015 | |
9 | Grant application considered by grant funders | 01/06/2015 | 17/09/2015 |
10 | Stage 1 grant offered | 17/09/2015 | 17/09/2015 |
11 | Assuming HLF grant obtained, specification, schedule of works, and drawings prepared; tender package and budget costs for repair works prepared | 18/09/2015 | 18/11/2015 |
12 | Tender package sent out to contractors | 19/11/2015 | 19/12/2015 |
13 | Permissions process undertaken (LBC or faculty, as appropriate) | 02/01/2016 | 06/01/2016 |
14 | Tenders returned | 13/01/2016 | 13/01/2016 |
15 | Tender report prepared | 16/01/2016 | 20/01/2016 |
16 | Chancellor considers faculty application | 09/01/2016 | 09/03/2016 |
17 | Stage 2 grant application submitted | 09/04/2016 | 09/04/2016 |
18 | Stage 2 grant received | 09/07/2016 | 09/07/2016 |
19 | Instruction issued to selected contractor to commence repair works | 15/08/2016 | 15/09/2016 |
20 | Contractor commences repair works | 16/09/2016 | 15/10/2016 |
21 | Repair of turrets complete | TBC | TBC |
Prepared by London Diocese, Anglican Church, December 2014.